Project Update Images
-
-
-
-
- 9th floor block work is completed.
- 10th floor block work is completed
- Upto 7th floor inner plastering work is completed
- 8th floor inner plastering work is in progress. (50% completed)
- Upto 8th floor toilet plumbing work is in progress.
- Corridor flooring work is in progress.
- STP sump work is in progress.
- Lift erection work is in progress. (2/4 completed & 1 progress)
- External plastering work is in progress. (75% completed).
- Upto 7th floor inner plastering work is completed
- 8th floor inner plastering work is in progress. (60% completed)
- Upto 8th floor toilet plumbing work is in progress.
- Corridor flooring work is in progress.
- STP sump work is in progress.
- Lift erection work is in progress. (2/4 completed & 1 progress)
- External plastering work is in progress. (80% completed).
- Upto 7th floor inner plastering work is completed
- 8th floor inner plastering work is in progress. (70% completed)
- Upto 8th floor toilet plumbing work is in progress.
- Upto 3rd floor Corridor flooring work is completed.
- Toilet wall tile laying work is in progress (32 Flats completed)
- STP sump work is in progress.
- Lift erection work is in progress. (2/4 completed & 1 progress)
- External plastering work is in progress. (80% completed).
- Model flat work is in progress.
- Upto 8th floor inner plastering work is completed
- 9th floor inner plastering work is in progress. (50% completed)
- Upto 8th floor toilet plumbing work is in progress.
- Upto 5th floor Corridor flooring work is completed.
- Toilet wall tile laying work is in progress (55 Flats completed)
- General floor tile laying work is in progress (15 Flats completed)
- STP sump 1, work is completed.
- Lift erection work is in progress. (3/4 completed & 1 progress)
- Upto 7th floor staircase flooring work is completed.